Cost estimate
Wood deck (pressure-treated)
What building a low pressure-treated wood deck can cost per square foot, without railing or stairs, built from published wages and shelf prices.
Data last checked . Every input is dated below.
Typical cost
Planning range $3,800 to $10,000
About $28.75 per sq ft, typical.
Where the money goes
- Labor$2,20032%
- Materials$1,75025%
- Permits and inspections$2504%
- Haul-away and disposal$100%
- Contractor overhead and profit$2,70039%
For information only. A planning range, not a quote. We take care, but our sources can lag and so can we, so a figure may be out of date. It combines the low end of every input and the high end of every input, so it is deliberately wide. Real quotes can still fall outside it.
What moves the price
The same job can quote very differently. These are the usual reasons.
- Height and railing
- A deck more than about 30 inches above the ground needs a railing, and stairs are extra. Both can add a lot and are not in these figures.
- Decking material
- Pressure-treated pine is the lowest-cost option. Cedar, hardwood and composite boards cost more to buy and some take less upkeep.
- Footings and soil
- Frost depth, soft or sloped ground and rock change how deep and how many footings are needed.
- Attachment to the house
- Flashing the ledger board properly keeps water out of the wall. A free-standing deck needs extra posts and beams instead.
- Permit and inspection
- Most towns require a permit for an attached deck. Fees and the number of inspections vary.
- Lumber prices
- Lumber prices move through the year. The shelf prices here were read on one day.
The same job at other sizes, and in each state
Both tables use the same estimate as the calculator above. They are here to read across; the calculator takes your own size and state.
| Size | Typical | Range | Per sq ft |
|---|---|---|---|
| 100 sq ft | $3,550 | $2,500 to $4,600 | $35.29 |
| 230 sq ft | $6,650 | $3,650 to $9,650 | $28.83 |
| 350 sq ft | $9,850 | $5,400 to $14,300 | $28.21 |
| 480 sq ft | $13,400 | $7,400 to $19,300 | $27.89 |
| 600 sq ft | $16,600 | $9,300 to $24,000 | $27.71 |
Small jobs cost more per sq ft because a contractor has a minimum charge, and the per-unit figure falls as the job grows until the minimum no longer applies.
Cost by state, at 240 sq ft
| State | Typical | Range | Against the US average |
|---|---|---|---|
| Alabama | $5,850 | $3,300 to $8,400 | −15% |
| Alaska | $7,900 | $4,200 to $11,600 | +15% |
| Arizona | $6,400 | $3,550 to $9,250 | −7% |
| Arkansas | $5,850 | $3,300 to $8,450 | −15% |
| California | $7,850 | $4,200 to $11,500 | +14% |
| Colorado | $6,900 | $3,800 to $10,100 | about the same |
| Connecticut | $7,000 | $3,800 to $10,200 | +2% |
| Delaware | $6,650 | $3,650 to $9,600 | −4% |
| District of Columbia | $7,150 | $3,900 to $10,400 | +4% |
| Florida | $6,150 | $3,450 to $8,800 | −11% |
| Georgia | $6,000 | $3,400 to $8,600 | −13% |
| Hawaii | $8,500 | $4,500 to $12,400 | +23% |
| Idaho | $6,250 | $3,500 to $9,000 | −9% |
| Illinois | $7,850 | $4,200 to $11,500 | +13% |
| Indiana | $6,700 | $3,650 to $9,750 | −3% |
| Iowa | $6,250 | $3,450 to $9,000 | −10% |
| Kansas | $6,350 | $3,500 to $9,200 | −8% |
| Kentucky | $6,150 | $3,450 to $8,850 | −11% |
| Louisiana | $5,900 | $3,300 to $8,500 | −15% |
| Maine | $6,700 | $3,650 to $9,700 | −3% |
| Maryland | $7,200 | $3,900 to $10,500 | +4% |
| Massachusetts | $7,650 | $4,100 to $11,300 | +11% |
| Michigan | $6,600 | $3,600 to $9,550 | −5% |
| Minnesota | $7,150 | $3,900 to $10,500 | +4% |
| Mississippi | $5,850 | $3,300 to $8,350 | −16% |
| Missouri | $6,700 | $3,700 to $9,750 | −3% |
| Montana | $6,450 | $3,550 to $9,300 | −7% |
| Nebraska | $6,100 | $3,400 to $8,800 | −12% |
| Nevada | $7,000 | $3,800 to $10,200 | +1% |
| New Hampshire | $6,800 | $3,750 to $9,850 | −2% |
| New Jersey | $7,500 | $4,100 to $10,900 | +9% |
| New Mexico | $6,300 | $3,500 to $9,100 | −9% |
| New York | $7,700 | $4,200 to $11,300 | +12% |
| North Carolina | $5,950 | $3,350 to $8,500 | −14% |
| North Dakota | $6,300 | $3,500 to $9,100 | −9% |
| Ohio | $6,500 | $3,550 to $9,450 | −5% |
| Oklahoma | $5,800 | $3,250 to $8,300 | −16% |
| Oregon | $7,350 | $4,000 to $10,700 | +7% |
| Pennsylvania | $6,750 | $3,700 to $9,750 | −2% |
| Rhode Island | $6,750 | $3,700 to $9,800 | −2% |
| South Carolina | $6,200 | $3,450 to $8,950 | −10% |
| South Dakota | $5,950 | $3,350 to $8,500 | −14% |
| Tennessee | $6,100 | $3,400 to $8,800 | −11% |
| Texas | $6,000 | $3,400 to $8,650 | −13% |
| Utah | $6,200 | $3,450 to $9,000 | −10% |
| Vermont | $6,600 | $3,650 to $9,600 | −4% |
| Virginia | $6,450 | $3,600 to $9,350 | −6% |
| Washington | $7,800 | $4,200 to $11,400 | +13% |
| West Virginia | $6,200 | $3,450 to $8,900 | −10% |
| Wisconsin | $6,700 | $3,650 to $9,750 | −3% |
| Wyoming | $6,400 | $3,550 to $9,250 | −7% |
Each state's wages for this trade, material price level and permit level are applied to the same job. They are statewide averages; towns within a state differ, and an expensive city and a rural county can sit far apart.
How we got these numbers
Labor, parts, overhead and permits, added up. Each assumption below says how solid it is.
- Our estimateLabor hours of 0.15 to 0.30 a square foot (for 240 sq ft, 36 to 72 hours across the crew, covering footings, posts, beam, joists, ledger, decking and cleanup) are our estimate: we found no time study.
- Checked sourceMaterials of $5.50 to $8.00 a square foot are our parts list priced at Lowe's shelf prices on 5 Nov 2026 for a 12 by 16 ft deck: 2 x 8 joists at 16 inches, a doubled 2 x 10 beam, three 6 x 6 posts on concrete footings, 5/4 x 6 deck boards at $10.33 to $13.98 a 12-ft board, joist hangers, screws and flashing tape. The quantities are our arithmetic and the top end allows for larger lumber and extra hardware.
- Our estimate8% waste covers cuts and warped boards.
- Checked sourcePermit fees of $100 to $400: Albany NY charges $100 plus $8 per $1,000 of cost over $5,000, which is about $116 for a $7,000 deck; the other schedules do not list decks, so the top end is our allowance for plan review and higher-priced places.
- Checked sourceWages are for carpenters.
- Checked sourcePayroll costs of 21% to 27% of wages follow the Census 2022 figure for finish carpentry contractors (fringe benefits 23.0% of payroll).
- Checked sourceOverhead and profit of 50% to 70% is added on top of wages with payroll costs, materials, permits and disposal. Census 2022: these contractors' receipts were 60% above direct cost; NAHB's remodeler study gives 43%.
- Checked sourceCross-check: the Census figure of $176 of work per field labor-hour for finish carpentry contractors (the group the NAICS 2022 index puts deck construction in). Our typical figure works out within a factor of two of it. No federal cost database covers decks.
- Not includedRailing, stairs, built-in benches, lighting, composite or hardwood boards, a roof or pergola, grading, and engineering for tall or large decks are not included.
Sources
Where each input comes from, and when we last looked.
- Checked sourceU.S. Bureau of Labor Statistics, Occupational Employment and Wage Statistics (OEWS). Data year 2025, checked 2026-11-04.
- Checked sourceU.S. Census Bureau, 2022 Economic Census, table EC2223BASIC (Construction: Summary Statistics), NAICS 238350 Finish Carpentry Contractors (the NAICS 2022 index lists residential deck construction here), United States; fringe benefits are 23.0% of payroll, revenue is 60% above direct cost and the value of work is $176 per field labor-hour. Data year 2022, checked 2026-11-05.
- Checked sourceLowe's shelf prices read on lowes.com, Columbus OH store, 5 Nov 2026: pressure-treated 5/4 x 6 x 12 ft deck boards $10.33 to $13.98, 2 x 8 x 12 ft joists $22.09, 2 x 10 x 12 ft and 16 ft beam lumber $25.98 and $36.78, 6 x 6 x 8 ft posts $39.04, joist hangers $2.58, deck screws $29.98 to $39.98 a box, 50 lb concrete $7.97. Data year 2026, checked 2026-11-05.
- Our estimateNo official or trade time study found. The hours are our estimate for a two-person crew building a low, attached, pressure-treated deck including footings, framing and decking, bounded by the Census figure of $176 of work per field labor-hour. Data year 2022, checked 2026-11-05.
- Published, secondhandNAHB Remodelers' Cost of Doing Business Study, 2026 edition (fiscal 2024), as reported by NAHB's Eye on Housing blog, 8 Apr 2026: revenue about 43% above direct cost (33% in 2021). Data year 2024, checked 2026-11-04.
- Checked sourceOfficial city building permit fee schedules read 5 Nov 2026: City of Auburn CA (building fees, 24 May 2025), City of Pleasanton CA (building permit and plan review fees) and City of Albany NY (building and zoning permit application fees, revised Feb 2026). Three small or mid-size cities, not a national survey; fees in larger cities and valuation-based schedules can be higher. Data year 2026, checked 2026-11-05.
- Our estimateOur working assumptions, marked as estimates on this page; not checked against contractor quotes. Data year 2026, checked 2026-11-05.
- Published, secondhandU.S. Bureau of Economic Analysis, Regional Price Parities by state (US = 100), as republished by FRED (Federal Reserve Bank of St. Louis). Goods parity is used for materials and all-items parity as a rough stand-in for permit fees. Data year 2024, checked 2026-11-04.